Evidence room for a neighborhood emergency planner. Question dated ; packet frozen as of that date.

Should ERCOT's published winter reserve be represented as a guarantee for an extreme cold event?

Answer

No. Treat it as a planning estimate, not a guarantee.

ERCOT's final winter SARA for December 2020 through February 2021 shows 16,198 MW of capacity available for operating reserves in the forecast case, but only 1,352 MW in its extreme peak load and extreme generation outage case. ERCOT labels that row “Capacity Available for Operating Reserves, Normal Operating Conditions” and builds it from historical averages and percentiles. ST1 ERCOT SARA

If every other extreme-case assumption stayed fixed, that reserve would reach zero when thermal forced outages total 11,231 MW, which is 1,352 MW more than the 9,879 MW the SARA assumes in that column. ST1 ERCOT SARA

In 2011, FERC and NERC staff wrote that ERCOT and others “had adequate reserve margins, based on anticipated generator availability” but “those reserves proved insufficient.” ST2 FERC/NERC 2011

Decision: before , adopt a neighborhood extreme cold plan that assumes rotating outages can happen during a multi-day freeze even when published reserves look adequate. Specific actions below. No probability is assigned to any storm, and no motive is alleged.

Remaining operating reserve in each SARA column

Capacity available for operating reserves, four SARA columns, MW Zero-baseline horizontal bars. Values: Forecasted Season Peak Load 16,198 MW; Extreme Peak Load, Typical Generation Outages 5,892 MW; Forecasted Season Peak Load, Extreme Low Wind Output 10,919 MW; Extreme Peak Load, Extreme Generation Outages 1,352 MW. Forecasted Season Peak Load (forecast case) 16,198 MW ST1 row [e], column 1 Extreme Peak Load with Typical Generation Outages 5,892 MW ST1 row [e], column 2 Forecasted Season Peak Load with Extreme Low Wind Output 10,919 MW ST1 row [e], column 3 Extreme Peak Load with Extreme Generation Outages 1,352 MW ST1 row [e], column 4 0 5,000 10,000 15,000 20,000 MW (zero baseline)
Row [e], “Capacity Available for Operating Reserves, Normal Operating Conditions (c-d)”, for the four columns in printed order. Bars start at zero MW. The red bar is the extreme load and extreme outage column. ST1 ERCOT SARA

Reconciliation: every baseline number

All four columns share Total Resources 82,513 MW, Peak Demand 57,699 MW and Reserve Capacity 24,814 MW. Each column then subtracts its own adjustments; the recomputed totals match the printed rows [d] and [e] exactly in all four columns. ST1 ERCOT SARA

The 19 listed resource lines sum to 82,514 MW, 1 MW above the printed total, consistent with rounding; the published reserve uses the printed total. ST1 ERCOT SARA

The extreme peak forecast of 67,208 MW equals Peak Demand plus the 9,509 MW Seasonal Load Adjustment, and the SARA bases it on the 2011 winter. The summary outage forecast of 8,616 MW equals forecast case maintenance plus typical forced outages. ST1 ERCOT SARA

Wind: the 6 wind lines contribute 7,070 MW; the low wind level is 1,791 MW; the difference is the printed 5,279 MW Low Wind Output Adjustment. ST1 ERCOT SARA

Forecasted Capacity and Demand, MW, as printed on SARA page 2 ST1 ERCOT SARA
LineMWSource
Operational Resources (thermal and hydro), MW67,529ST1 line 9
Switchable Capacity Total, MW3,710ST1 line 10
Less Switchable Capacity Unavailable to ERCOT, MW-568ST1 line 11
Available Mothballed Capacity, MW0ST1 line 12
Capacity from Private Use Networks, MW3,631ST1 line 13
Coastal Wind, Peak Average Capacity Contribution, MW1,480ST1 line 14
Panhandle Wind, Peak Average Capacity Contribution, MW1,411ST1 line 15
Other Wind, Peak Average Capacity Contribution, MW3,251ST1 line 16
Solar Utility-Scale, Peak Average Capacity Contribution, MW269ST1 line 17
Storage, Peak Average Capacity Contribution, MW0ST1 line 18
RMR Capacity to be under Contract0ST1 line 19
Capacity Pending Retirement, MW0ST1 line 20
Non-Synchronous Ties, Capacity Contribution, MW838ST1 line 21
Planned Thermal Resources with Signed IA, Air Permits and Water Rights, MW0ST1 line 22
Planned Coastal Wind with Signed IA, Peak Average Capacity Contribution, MW371ST1 line 23
Planned Panhandle Wind with Signed IA, Peak Average Capacity Contribution, MW0ST1 line 24
Planned Other Wind with Signed IA, Peak Average Capacity Contribution, MW557ST1 line 25
Planned Solar Utility-Scale, Peak Average Capacity Contribution, MW35ST1 line 26
Planned Storage, Peak Average Capacity Contribution, MW0ST1 line 27
Sum of the 19 listed lines (computed)82,514computed from ST1
[a] Total Resources (printed)82,513ST1
[b] Peak Demand (printed)57,699ST1
[c] Reserve Capacity [a - b] (printed; recomputed 24,814)24,814ST1
Range of Potential Risks, four columns in printed order, MW ST1 ERCOT SARA
LineS1. Forecasted Season Peak LoadS2. Extreme Peak Load, Typical Generation OutagesS3. Forecasted Season Peak Load, Extreme Low Wind OutputS4. Extreme Peak Load, Extreme Generation OutagesSource
Total Resources [a]82,51382,51382,51382,513ST1
Peak Demand [b]57,69957,69957,69957,699ST1
Reserve Capacity [c] = a - b24,81424,81424,81424,814ST1
Seasonal Load Adjustment0 (printed as a dash)9,5090 (printed as a dash)9,509ST1
Peak demand used (b + seasonal adjustment)57,69967,20857,69967,208ST1
Typical Maintenance Outages, Thermal4,0744,0744,0744,074ST1
Typical Forced Outages, Thermal4,5425,3394,5425,339ST1
95th Percentile Forced Outages, Thermal0 (printed as a dash)0 (printed as a dash)0 (printed as a dash)4,540ST1
Thermal forced outages, total (typical + 95th)4,5425,3394,5429,879ST1
Low Wind Output Adjustment0 (printed as a dash)0 (printed as a dash)5,2790 (printed as a dash)ST1
[d] Total Uses of Reserve Capacity (printed)8,61618,92213,89523,462ST1
[d] recomputed: seasonal + maintenance + forced + 95th + low wind8,61618,92213,89523,462ST1
[e] Capacity Available for Operating Reserves, Normal Operating Conditions (printed)16,1985,89210,9191,352ST1
[e] recomputed: c - d16,1985,89210,9191,352ST1

Thermal forced outage total that exhausts operating reserve

In the Extreme Peak Load, Extreme Generation Outages column the SARA assumes 5,339 MW of typical forced outages plus 4,540 MW at the 95th percentile, 9,879 MW in all, and leaves 1,352 MW. With every other assumption fixed, each extra MW of thermal forced outage removes one MW of reserve, so reserve reaches zero at 9,879 MW + 1,352 MW = 11,231 MW. ST1 ERCOT SARA

Cross-check: the Extreme Peak Load, Typical Generation Outages column reaches the same point, 5,339 MW + 5,892 MW = 11,231 MW. ST1 ERCOT SARA

This is arithmetic on published assumptions. Zero is the point of mathematical exhaustion, not the point where trouble starts: the packet does not give a 2020/2021 minimum reserve requirement, and in 2011 ERCOT had a 2,300 MW minimum responsive reserve requirement and reserves that “eventually dropped below the level of safe operation.” ST1 ERCOT SARA ST2 FERC/NERC 2011

Sensitivity: hypothetical extra thermal forced outages

Sensitivity, not a measurement or prediction The control adds a hypothetical amount to the thermal forced outages of the extreme load and extreme outage column and holds everything else fixed. It does not report any measured outage and does not forecast one.

Published SARA column (fixed)

Immutable Extreme Peak Load / Extreme Generation Outages During Extreme Peak Load

Thermal forced outages 9,879 MW
Remaining operating reserve 1,352 MW

ST1 ERCOT SARA

Hypothetical sensitivity

Static sensitivity table (works without JavaScript): hypothetical extra thermal forced outages in the Extreme Peak Load, Extreme Generation Outages column, from ST1 ERCOT SARA
Hypothetical extra thermal forced outagesTotal thermal forced outagesRemaining operating reserveState
0 MW9,879 MW1,352 MWabove zero
500 MW10,379 MW852 MWabove zero
1,000 MW10,879 MW352 MWabove zero
1,352 MW11,231 MW0 MWzero crossing
1,500 MW11,379 MW-148 MWexhausted
2,000 MW11,879 MW-648 MWexhausted
2,500 MW12,379 MW-1,148 MWexhausted
3,000 MW12,879 MW-1,648 MWexhausted

Normal operating reserve is not an instantaneous guarantee

The SARA row is titled “Capacity Available for Operating Reserves, Normal Operating Conditions (c-d)”. Its forced outage inputs are historical averages for December through February weekdays, hours ending 7 am - 10 am, over 2017/18, 2018/19, and 2019/20, and its 95th percentile row adds the fuel limitation derates of the January 17, 2018 event. ST1 ERCOT SARA

The SARA summary says ERCOT “anticipates there will be sufficient installed generating capacity available to serve system-wide forecasted peak demand this winter season”; its peak forecast is based on normal weather conditions during peak periods, from 2004 through 2018. That statement concerns forecasted peak demand, not the extreme columns. ST1 ERCOT SARA

An instantaneous operational guarantee would mean load is served at every moment of an event. The 2011 report shows why a positive planning reserve does not provide that: ERCOT started the first day with 3,100 MW of responsive reserves against a 2,300 MW minimum, and generator failures still “overwhelmed ERCOT’s reserves.” ST2 FERC/NERC 2011

The earlier FERC/NERC warning, in its own words

Exact sentences from the August 2011 staff report, printed pages 7 to 10. ST2 FERC/NERC 2011

“Going into the February 2011 storm, neither ERCOT nor the other electric entities that initiated rolling blackouts during the event expected to have a problem meeting customer demand.”

FERC/NERC staff, August 2011, packet line 4. ST2 FERC/NERC 2011

“They all had adequate reserve margins, based on anticipated generator availability.”

FERC/NERC staff, August 2011, packet line 4. ST2 FERC/NERC 2011

“But those reserves proved insufficient for the extraordinary amount of capacity that was lost during the event from trips, derates, and failures to start.”

FERC/NERC staff, August 2011, packet line 4. ST2 FERC/NERC 2011

“In the case of ERCOT, where rolling blackouts affected the largest number of customers (3.2 million), there were 3100 MW of responsive reserves available on the first day of the event, compared to a minimum requirement of 2300 MW.”

FERC/NERC staff, August 2011, packet line 6. ST2 FERC/NERC 2011

“But over the course of that day and the next, a total of 193 ERCOT generating units failed or were derated, representing a cumulative loss of 29,729 MW.”

FERC/NERC staff, August 2011, packet line 6. ST2 FERC/NERC 2011

“Combining forced outages with scheduled outages, approximately one-third of the total ERCOT fleet was unavailable at the lowest point of the event.”

FERC/NERC staff, August 2011, packet line 6. ST2 FERC/NERC 2011

“These extensive generator failures overwhelmed ERCOT’s reserves, which eventually dropped below the level of safe operation.”

FERC/NERC staff, August 2011, packet line 6. ST2 FERC/NERC 2011

“Generators and natural gas producers suffered severe losses of capacity despite having received accurate forecasts of the storm.”

FERC/NERC staff, August 2011, packet line 12. ST2 FERC/NERC 2011

“However, the poor performance of many of these generating units and wells suggests that these procedures were either inadequate or were not adequately followed.”

FERC/NERC staff, August 2011, packet line 12. ST2 FERC/NERC 2011

“These recommendations were not mandatory, and over the course of time implementation lapsed.”

FERC/NERC staff, August 2011, packet line 14. ST2 FERC/NERC 2011

“Many of the generators that experienced outages in 1989 failed again in 2011.”

FERC/NERC staff, August 2011, packet line 14. ST2 FERC/NERC 2011

“At least another 12 percent were indirectly attributable to the weather (occasioned by natural gas curtailments to gas-fired generators and difficulties in fuel switching).”

FERC/NERC staff, August 2011, packet line 9. ST2 FERC/NERC 2011

Cumulative 2011 loss versus a simultaneous outage

The 29,729 MW figure is a cumulative loss: it adds up 193 units that failed or were derated over that day and the next. It is not a simultaneous outage, and it cannot be set against the 11,231 MW single-column threshold above. ST2 FERC/NERC 2011

The report’s simultaneous measure is a fraction: combining forced and scheduled outages, approximately one-third of the total ERCOT fleet was unavailable at the lowest point of the event. The packet does not give the 2011 fleet size in MW, so that fraction cannot be converted into MW here. ST2 FERC/NERC 2011

Timeline from the packet

  1. Cold weather caused many generators to trip, derate, or fail to start; non-mandatory winterization recommendations followed and implementation lapsed. ST2 FERC/NERC 2011
  2. Southwest cold weather event; rolling blackouts in ERCOT affected 3.2 million customers. ST2 FERC/NERC 2011
  3. FERC/NERC staff report on causes and recommendations. ST2 FERC/NERC 2011
  4. ERCOT releases the final winter 2020/2021 SARA, the date of this question. ST1 ERCOT SARA
  5. Season the SARA covers. ST1 ERCOT SARA

What the SARA does not prove

These outage definitions and common-cause risks cannot be bounded from this packet. Each item names what the packet does say.

Proposed preparedness decision

Do not represent the SARA reserve as a guarantee. Before December 1, 2020, adopt a neighborhood extreme cold plan that assumes rotating outages can occur during a multi-day freeze even when published reserves look adequate.

  1. Build a roster of households that depend on powered medical equipment or electric heat, with a named check-in volunteer for each household.
  2. Designate one warming site with heat and backup power that does not depend on the grid, and test it before December 1, 2020.
  3. Set an activation trigger: a forecast of cold comparable to February 2011, or any grid conservation or emergency appeal.
  4. Keep a phone tree and printed contact sheet so outreach works without home power or internet.

Why: the extreme case leaves only 1,352 MW under normal operating conditions ST1; the extreme load basis is the 2011 winter ST1; and in 2011 reserves that looked adequate were overwhelmed by generator failures despite accurate forecasts ST2. This plan does not depend on knowing how likely a storm is, and it makes no claim about anyone’s intent.

Original official sources

Each link stores the original address, so it survives offline; opening it needs a connection. This page names no individual people and makes no claims about any person.

Generated by model.py from the packet text and verified by check.py. Sensitivity values are hypothetical.