Feasibility evidence room, frozen at December 22, 2022

25 Water Street: the bid cannot be priced yet

Finding as of December 22, 2022: a project-specific purchase bid for 25 Water Street cannot yet be priced. The only public record is a financing announcement. It gives the building size, a cited floor plate, a planned home count and a loan amount. It gives no construction cost, no income, no loan terms and no entitlement.

Decision status: blocked Break-even purchase price: not computed

Historical teaching case built only from what an analyst could see on December 22, 2022. Not investment or legal advice.

What the record says

Every figure below comes from one source, W1, the Newmark release of December 22, 2022, and keeps its own status. None of them is a test fit, a dwelling permit, a purchase price or a construction budget.

Published baseline figures
FigureValueStatus Source
Acquisition and redevelopment loan arranged$535.8 millionAnnounced financing. Not the purchase price, total cost, construction budget, net sale proceeds or a bid.W1, Dec 22, 2022
Height22 storiesPublished building description.W1, Dec 22, 2022
Office gross area1.1 million sq ftPublished, rounded office area. Not residential net area or a test fit.W1, Dec 22, 2022
Representative floor plate40,330 sq ft per floorCited size of the floor plates. Not measured floor by floor and not multiplied by the story count here.W1, Dec 22, 2022
Slab-to-slab height12 ft 4 inPublished dimension.W1, Dec 22, 2022
Announced homesapproximately 1,300 homesIssuer plan. Not a dwelling permit, test fit or certified occupancy limit.W1, Dec 22, 2022
Announced dwelling rangestudios to four bedroomsIssuer plan. Dwelling mix and minimum unit size unknown.W1, Dec 22, 2022
Year built1969Published.W1, Dec 22, 2022
Light and airuninterrupted on three sidesQualitative issuer claim. No measured window schedule.W1, Dec 22, 2022

One floor, one unit of area

One cited floor plate shown as one unit of area Solid outline: one floor plate of 40,330 sq ft cited in W1. Hatched region: unknown window exposure, usable depth and core. Its size and position are not measured; the shape is a placeholder. ?
  • Whole outline: 1 floor plate = 40,330 sq ft, the cited size of the floor plates. Used as one unit of area.
  • Unknown window and core region. Window exposure, usable depth and core size are not measured. Shape and size are placeholders, not an estimate.

Not to scale: the release gives no plate dimensions. Source: W1, Dec 22, 2022

Separate future plan

Approximately 1,300 homes, studios to four bedrooms, are announced for after redevelopment.

This is the issuer's plan. It is not a dwelling permit, not an architect's test fit and not a certified occupancy limit. It is kept apart and is never used as a denominator on this page.

Source: W1, Dec 22, 2022

Conditional one-floor scenario HYPOTHETICAL

Hypothetical, one example floor. The cited 40,330 sq ft floor plate is the only sourced number here, used as an example one-floor denominator. The usable share and the average unit area are your assumptions. They are not site measurements, not a test fit and not a project unit-count estimate.

Without measured window schedules even the usable-area assumption cannot be validated.

Assumptions in view: 60% usable of one 40,330 sq ft floor, 750 sq ft average unit. Both hypothetical.

Hypothetical conditional area on one example floor: 24,198 sq ft

Hypothetical units that would fit that area on this one floor: 32

Rule: 40,330 sq ft x 60% = 24,198 sq ft, then divided by 750 sq ft and rounded down. Not a count of permitted apartments, not a whole-building test fit.

Area on one example floor, in sq ft only. Both bars start at zero.

Cited floor plate: 40,330 sq ft

Hypothetical usable share at 60%: 24,198 sq ft

Zero baseline: 0 sq ft at the left line.

Break-even purchase ceiling: unsolved

Pmax = N + L - (H + S + C + K + O)

Pmax = not computed. Decision status: blocked. Every term on the right side is missing as of December 22, 2022. No blank is filled with zero, a market guess, an illustrative price or a later number.

N
Net sale proceeds at exit: sale value minus sale costs. Missing: exit assumption, income, taxes and operating expenses.
L
Net lease-up cash before exit. Missing: resident income and rent mix, operating expenses, taxes and time to occupancy.
H
Hard construction cost. Missing: no bid or contract, no measured plans.
S
Soft cost: design, permits, legal and fees. Missing.
C
Contingency. Missing.
K
Carrying cost during works: interest, taxes, insurance. Missing: lender interest terms, draw dates, loan split and time to occupancy.
O
Other project costs, including any required return. Missing.

The $535.8 million loan is financing for acquisition and redevelopment. It is not N, not Pmax, not a purchase price and not a bid.

Why the decision is blocked

Unanswered inputs

Inputs that must be signed or sourced before any bid
InputWould come from Status
Acquisition consideration actually paidSigned purchase agreement or recorded deedMissing
Loan split between acquisition and redevelopmentExecuted loan agreementMissing
Lender interest termsTerm sheet with index, spread or coupon, fees and reservesMissing
Construction draw datesLender-approved draw scheduleMissing
Hard cost (H)Signed contractor bid or guaranteed maximum priceMissing
Soft cost (S)Design, permit, legal and financing fee budgetMissing
Contingency (C)Budget with a stated contingencyMissing
Carrying cost (K)Interest, taxes and insurance during works, from loan terms and scheduleMissing
Other project costs (O)Closing costs, required return and any other line itemsMissing
Full resident income and rent mixUnit-by-unit rent roll and any income or affordability termsMissing
Real estate taxesAssessment and tax treatment in force on December 22, 2022Missing
Operating expensesResidential operating budgetMissing
Time to occupancyConstruction schedule and certificate of occupancy pathMissing
Lease-up cash (L)Lease-up schedule net of operating costsMissing
Exit assumptionExit timing, value basis and sale costsMissing
Net sale proceeds (N)Follows only from the exit assumption, income and sale costsMissing
Entitlement: code and zoning review, dwelling permitFiled plans, code review and permit recordMissing
Measured plans and window scheduleArchitect's measured drawings for every floorMissing
Unit test fit, dwelling mix, minimum unit sizeArchitect's test fit checked against codeMissing

Unknown until measured plans and code review arrive

Next five diligence requests

  1. Measured architectural plans for every floor, with a facade window schedule, core outlines and window-to-core depths, so daylight-served area is measured instead of assumed.
  2. An architect's unit test fit with dwelling mix and minimum unit sizes, plus a code and zoning review and the dwelling permit filing status as of December 22, 2022.
  3. A signed or bid construction budget: hard cost, soft cost and contingency, with the construction draw dates and the expected time to occupancy.
  4. The executed loan terms: how the $535.8 million loan splits between acquisition and redevelopment, rate or spread and index, fees, reserves, draw conditions and maturity.
  5. An income and exit underwrite: full resident income and rent mix by unit type, real estate taxes under rules in force on December 22, 2022, operating expenses, lease-up timing and the exit assumption with sale costs.

Timeline known on the record date

  1. 1969: building completed (W1).
  2. December 22, 2022: financing announced for acquisition and redevelopment (W1). Record frozen here.

Sources and scope